Environmental Fund Selects Contractor for Gospić Waste Cleanup
The Environmental Protection Fund and Energy Efficiency Fund officially selected a contractor on November 10, 2026, to remediate 4,500 tons of hazardous waste located near the silo of the former PPK Velebit in Gospić. This significant decision follows a rapid public procurement negotiation process, establishing a clear path toward environmental restoration in the region. The chosen consortium is responsible for removing the waste and ensuring its energy recovery abroad within a strict timeframe. This action marks a crucial step in addressing the long-standing issue of dumped materials at the site.
Contract Details and Timeline
The contract value for this phase of remediation, excluding VAT, was set at 7.87 million euros, according to the official announcement from the Fund. The selected group of bidders comprises Saubermacher TS, C.I.A.K., Kemis-Termoclean, and Kemokop d.o.o. The Fund's Administrative Board approved the selection, and the decision will be submitted to the Croatian Government after the legal waiting period expires. Furthermore, Franolić projekti has been appointed to manage the supervision of the actual execution of the remediation works.
In addition to the hazardous waste, the Fund announced that the removal of bulky waste from the former PPK Velebit location will commence during the current week. This bulky waste consists of wooden pallets, several car shells, and old tires, which will be managed by authorized collectors. This initial removal is intended to facilitate easier access for the trucks and heavy machinery required for the main hazardous waste cleanup and the remediation of buried waste sections.
Stakeholder Oversight and Next Steps
The Fund emphasized that the decision to select the contractor represents a vital advancement in the process of removing the dumped waste adjacent to the Gospić silo. If no appeals are filed against the decision, the transportation of the hazardous waste is scheduled to begin before the end of the current year. Previously, all non-hazardous waste contained in large bags near the facilities had been transported for energy recovery to the cement plants Nexe and Holcim, following all prescribed control measures.
The Fund also noted that the process for managing the bulky waste is currently underway, with negotiations ongoing for its proper disposal. This ongoing effort aims to clear the site systematically, ensuring that the hazardous waste removal can proceed without logistical impediments. The Fund remains committed to ensuring the energy recovery of the hazardous materials in foreign facilities as mandated by the contract terms.
The administrative board of the Fund confirmed that the selection was made following a rapid negotiation procedure for public procurement, ensuring a swift response to the environmental crisis. The Fund stated that the selection of the contractor is a significant step toward resolving the contamination issue at the Gospić site. The next procedural step involves submitting the final decision to the Croatian Government once the statutory waiting period has concluded.